CONSUMER INFORMATION FOR SERVICE CONNECTION
- When
consumer calls and all information is received in the service
department,
deposit has to be received and in the office before
request will be approved.
For deposit information,
click here.
- If
consumer has an existing pole and transformer within 100'
of the meter loop and no conflict occurs, such as service
wire traveling over the residence or outbuildings or a reason
where electrical codes will be violated. The consumer can
expect service to be connected within 4 working days following
receipt of a completed service order.
-
If consumer is building or setting up a new home or mobile
home, and there is no power line within 100' of the location,
or the service will have to run across a road. This is where
a span of primary will have to be constructed, and in some
instances right-of-way may have to be cleared and or obtained,
there is a minimum of 10 working days to complete service
order.
- When
consumer is building a house, setting up a mobile home, or
a deer camp or recreational facility and the nearest power
line is over 1000', provided the right-of-way is obtained
and cleared a minimum of 14 to 21 working days is required
to complete the service request.
- Yard
light installation whether on existing pole or if a pole has
to be set up for the yard light, a minimum of 14 to 21 working
days will be required.
|